Description / Abstract:
This specification covers requirements for hot weather concrete
construction.
This specification supplements the contract documents and
provides requirements for the Contractor.
This specification governs for construction within its scope,
but the contract documents govern if there is a conflict.
This specification governs if there is a conflict with its
reference standards.
The Contractor is permitted to submit written alternatives to a
provision in the specification.
Do not use this specification in conjunction with ACI 301,
350.5, 522.1, or ACI 530.1 unless contract document states that
this specification governs for work covered by 1.1.1.
Ignore provisions of the specification that are not applicable
to the work.
Values to this specification are stated in inch-pound units. A
companion specification in SI units is also available.